Date/Time: Calculate Number of Working Days

Author(s)
Arvin Meyer

(Q)    How do I calculate total number of working days between two dates?

(A)    Use one of the following functions.

'*********** Code Start **************
Public Function WorkingDays(StartDate As Date, EndDate As Date) As Integer
'....................................................................
' Name: 	WorkingDays
' Inputs: 	StartDate As Date
' 	EndDate As Date
' Returns: Integer
' Author: Arvin Meyer
' Date: 	February 19, 1997
' Comment: Accepts two dates and returns the number of weekdays between them
' Note that this function does not account for holidays.
'....................................................................
On Error GoTo Err_WorkingDays

Dim intCount As Integer

StartDate = StartDate + 1
'If you want to count the day of StartDate as the 1st day
'Comment out the line above

intCount = 0
Do While StartDate <= EndDate
'Make the above < and not <= to not count the EndDate

Select Case WeekDay(StartDate)
Case Is = 1, 7
intCount = intCount
Case Is = 2, 3, 4, 5, 6
intCount = intCount + 1
End Select
StartDate = StartDate + 1
Loop
WorkingDays = intCount

Exit_WorkingDays:
Exit Function

Err_WorkingDays:
Select Case Err

Case Else
MsgBox Err.Description
Resume Exit_WorkingDays
End Select

End Function


Public Function WorkingDays2(StartDate As Date, EndDate As Date) As Integer
'....................................................................
' Name: 	WorkingDays2
' Inputs: 	StartDate As Date
' 	EndDate As Date
' Returns: Integer
' Author: Arvin Meyer
' Date: 	May 5,2002
' Comment: Accepts two dates and returns the number of weekdays between them
' Note that this function has been modified to account for holidays. It requires a table
' named tblHolidays with a field named HolidayDate.
'....................................................................
On Error GoTo Err_WorkingDays2

Dim intCount As Integer
Dim rst As DAO.Recordset
Dim DB As DAO.Database

Set DB = CurrentDb
Set rst = DB.OpenRecordset("SELECT [HolidayDate] FROM tblHolidays", dbOpenSnapshot)

'StartDate = StartDate + 1
'To count StartDate as the 1st day comment out the line above

intCount = 0

Do While StartDate <= EndDate

rst.FindFirst "[HolidayDate] = #" & StartDate & "#"
If Weekday(StartDate) <> vbSunday And Weekday(StartDate) <> vbSaturday Then
If rst.NoMatch Then intCount = intCount + 1
End If

StartDate = StartDate + 1

Loop

WorkingDays2 = intCount

Exit_WorkingDays2:
Exit Function

Err_WorkingDays2:
Select Case Err

Case Else
MsgBox Err.Description
Resume Exit_WorkingDays2
End Select

End Function

'*********** Code End **************